The bottom cone of the vessel is set down at Kalamia Mill.

The last of four new evaporators is being installed in a $25 million capital replacement program at Wilmar Sugar and Renewables’ Kalamia Mill. All of the new vessels were engineered, fabricated and installed in-house. Manager projects David Innes said the fabrication and transport of the last vessel took more than 10,000 labour-hours. “Approximately 100 tonnes […]