Towering achievement for major transmission project

The first of 348 transmission towers has been built for Powerlink’s $295 million Genex Kidston Connection Project.

The project will see 186km of transmission line installed to connect Genex Power’s Kidston Clean Energy Hub and the Guybal Munjan switching station at Mount Fox.

Each transmission tower on the route will be about 50m tall and construction is expected to involve 5500 tonnes of galvanised steel.

“The construction of these towers means we are one step closer in enabling the flow of clean energy into communities across North Queensland,” project director Tony Janas said.

“In coming weeks, we will be using innovative drone technology to string the wires that will eventually connect the pumped hydro project to the grid.

“New control buildings have also arrived in Brisbane to complete factory acceptance testing before being deployed to the Aurumfield switching station. 

“These buildings will feature leading technology and are a critical part in maintaining security and reliability of electricity out of the pumped hydro system to North Queensland.”

Related: Work packages roll out for $5b CopperString project

The project was a key commitment by the State Government, announced during the regional parliament sitting in Townsville in 2019.

Weather-dependent, the project is expected to be completed by mid-to-late 2024.

Genex Power last week announced a milestone of its own in the construction of its pumped storage hydro project at the Kidston Clean Energy Hub.

It has completed the Main Access Tunnel (MAT) for underground works and remains on track for energisation next year.

The Kidston Pumped Storage Hydro Project is the first pumped hydro project in Australia for over 40 years, the first to be developed by the private sector, and the third largest electricity storage device in the country.