Tartana operation battling weather hitches
Heavy weather is hampering production at R3D Resources’ Tartana operation, impacting access to the site and supplies.
The company was able to resume production at the far north Queensland copper sulphate operation on January 5 following a halt in production due to Cyclone Jasper and the holiday break.
Activities on site in the past week had provided confidence in reaching a ‘free-flowing’ production state, managing director Stephen Bartrop said.

But the weather conditions continued to affect the team’s ability to operate onsite at Chillagoe and source required input materials including diesel and acid, he said.
“We are working closely with our 100 per cent offtake partner, Kanins, to target our first shipment being sent within the coming days, which will represent the first revenues from the plant,” Mr Bartrop said.
The heap leach-solvent extraction plant previously operated for about a decade under other owners before being placed in care and maintenance in 2014.
It came back into commercial production late last year following plant refurbishments under R3D.
Meanwhile the company is extending a rights issue until January 29. This is intended to raise $1.48 million on top of a placement in November that added $436,000 to company coffers.
Shareholders have approved a change in the company’s name from R3D Resources Limited to Tartana Minerals Limited.
However the ASX is yet to confirm a timetable for the company’s name change and corresponding ASX code change.