Tartana Minerals trucks out first copper sulphate load

Tartana Minerals is celebrating the first shipment of copper sulphate pentahydrate to leave its newly recommissioned plant for offtake partners Kanins.

Tartana Minerals managing director Stephen Bartrop hailed the load as reflecting a coalescence of more than two years of work in recommissioning the Chillagoe region plant.

The heap leach-solvent extraction plant at Tartana previously operated for about a decade under other owners before being placed in care and maintenance in 2014.

“We now look towards moving into a more regular rhythm of shipments being completed,” Dr Bartrop said.

“Recent copper price improvements directly increase the profitability of this project as copper sulphate is priced by reference to its copper weight plus a premium.”

Tartana has been paid for the product immediately upon its leaving the mine site and said cash receipts from Kanins would be reflected in its quarterly cash flow reporting.

Minimum shipments are 28 bags weighing about 1.2 tonnes each, with the product comprising 25 per cent copper.

Below: The first shipment ready to leave the Tartana mine site on May 3.