Tag: shutdown

Dragline shutdown a boost for Moura region

Principal contractor G&S Engineering is completing a three-month dragline maintenance shutdown at Anglo American’s Dawson mine, bringing about 250 extra workers to the Moura region.

Dawson mine general manager Clarence Robertson said the planned shutdown of the mine’s Dragline 4 commenced in February.

“The planned maintenance program involves electrical, mechanical and structural repairs and improvements to the machine to ensure it continues to safely operate into the future," he said.

"This includes replacing the dragline tub, a section of the revolving frame, boom repairs and cord replacement, as well as a major electrical system upgrade. . .

This content is available to Monthly Membership and Annual Membership members.

Join Monthly Membership · Join Annual Membership

Already a member?

Shutdown calendar to give Gladstone suppliers an edge

Gladstone industry leaders have launched a shutdown calendar to help supply chain businesses with planning.

The Gladstone Industry Leadership Group and Gladstone Engineering Alliance initiative outlines planned maintenance outages over a 12-18-month period.

It covers operations including Gladstone Ports Corporation, Rio Tinto Yarwun, Queensland Alumina Limited, Boyne Smelters Limited, Orica Yarwun, Cement Australia Yarwun, Gladstone Power Station, and the local LNG export facilities.

GEA general manager Chantale Lane said her team was thrilled to be able to work collaboratively with GILG to see the calendar up and running again.

“A current shutdown calendar is something our members have. . .

This content is available to Monthly Membership and Annual Membership members.

Join Monthly Membership · Join Annual Membership

Already a member?

Australian Professional Galvanizing will be adding an edge to its kettle and furnace set-up this month during a $1 million scheduled maintenance outage. at Townsville

Galvanising site gears up for $1m shutdown project

Australian
Professional Galvanizing will be adding an edge to its kettle and furnace
set-up this month during a $1 million scheduled maintenance outage.

Chief
executive officer Steve Pollard said the Townsville business was due to replace
the kettle – the vessel that holds molten zinc for the galvanising process.

“So we are
taking the opportunity while we are doing that to change the furnace design,”
he said. “It will be the first Therm-X in Australia.”

The business is receiving a $344,308 grant under the Made in Queensland (MiQ) program to install the Therm-X furnace system.

Mr Pollard. . .

This content is available to Monthly Membership and Annual Membership members.

Join Monthly Membership · Join Annual Membership

Already a member?

Subscribe to our news bulletin today and stay ahead with the latest news.