‘Not an exploration question’: copper’s bottleneck is the furnace
The world’s looming copper shortfall could not be solved by discovery alone, Banksia Minerals Processing chair and chief executive Leigh Staines said.
Ms Staines said the constraint lay in processing, a problem with direct consequences for North-West Queensland.
“It’s not an exploration question. We actually know where there’s plenty of copper available, but the issue is it’s not necessarily at a concentrate form that we can process easily,” she said.
Copper demand was forecast to rise 50 per cent by 2040, from 28 million tonnes to 42 million tonnes, S&P Global said in January.
Main image: Basksia Minerals Processing is developing a substitute processing for copper smelting like this at Mount Isa
Production was expected to peak at 33 million tonnes in 2030 and then fall. A shortfall of 10 million tonnes was forecast by 2040, even with recycling more than doubling.
Ms Staines said the pinch had been anticipated.
A substitute for the smelter
Brisbane-based Banksia Minerals Processing was established in 2024 to commercialise a copper refining process developed at The University of Queensland.

Related: MIM races the clock on smelter decision
The process was aimed at sulphide concentrates, the material now sent to smelters, Ms Staines said. It was not designed for oxide ores.
“What we’re talking about is a technology that can replace smelting,” she said. “We can also deal with much lower grade (ore) and we can deal with a much greater range of impurities,” she said.
Concentrate that would otherwise need blending could be taken directly, avoiding the associated penalties, she said.
What it means for the North West
Most North-West Queensland copper miners produced concentrate, Ms Staines said. Most of that concentrate went to Glencore’s Mount Isa smelter.
The smelter and the Townsville-based Copper Refineries were granted up to $600 million in government support over three years in October 2025.
Ms Staines said Banksia was examining a long-term alternative to the smelter, with scope to retrofit existing refining plant.
“So our business case looks at both smelter replacement options and also unlocking new resources as part of that,” she said.
Interest was not confined to Queensland. A major overseas producer with an ageing smelter fleet had raised replacing it with the process once de-risked, Ms Staines said.
Unproven at scale
The process had not yet been demonstrated beyond the laboratory. Ms Staines placed it in what she called ‘the missing middle’ of research and development.
A pilot plant is to be built in Brisbane over 2027, with test campaigns in 2028. The Australian Renewable Energy Agency approved up to $5 million towards the build in February.
A first commercial plant was targeted for 2031, Ms Staines said. Her preference was to build in Queensland.
“Once it’s technically proven, it’s commercially proven, it will be very hard to justify doing anything else,” she said.