New Century gets ducks in a row to start new mines

New Century Resources has ticked off all necessary environmental approvals to begin new mining operations at the Silver King and East Fault Block at the company’s Century zinc site.

At the same time, an optimisation study has showcased the highly attractive economics of mining those deposits, in addition to ongoing tailings reprocessing.

The company is targeting a Final Investment Decision (FID) in the second half of this year and first production by mid-2023.

The project is expected to require a $78.1 million investment over a 16-month development period.

“The New Century team is pleased to have achieved a major milestone toward development of Silver
King and East Fault Block through obtaining all necessary environmental approvals,” New Century managing director Patrick Walta said.

“The optimisation study has also reinforced the highly value-accretive potential of the in-situ
development at Century, materially expanding the production profile and life of asset while reducing
site-wide unit costs.

“The results underscore the significant near-term opportunity available via the development of Silver King and East Fault Block that will open up the avenue to continue the utilisation of approximately $2 billion previously invested in infrastructure at Century to 2030 and beyond.”

the porgress towards the new mining activitie shas not just happeneed on papaer. New Century said long lead items had been ordered to maintain critical path, including ball mill construction ( about 86 per cent complete) and securing initial underground mining equipment.

GR Engineering Services has completed the Front-End Engineering and Design (FEED) work, progressing to execution of engineering, procurement, and construction (EPC) contract.

The optimisation study showed the proposed insitu mining would bring a pre-tax NPV of $226 million at a base case, with IRR 91 per cent and pay back in 2.2 years.

On a spot case (based on current pricing) the porject would have a pre-tax NPV of $246 million, with IRR of 101 per cent and payback in 2.1 years.