New wells bring ‘step change’ for QPM energy business
Queensland Pacific Metals is kicking off a seven-well drilling program in what it describes as the next phase of its growth strategy at the Moranbah gas project.
The company announced today that it had a drilling rig on location to spud the first well of the Teviot Brook South program.
It comes after news of the company’s plans to step back from its TECH battery metals project in Townsville and switch its core focus to advancing its gas and energy assets.
Related: TECH on backburner as QPM ramps up energy ambitions
“The Teviot Brook South program will be the first new owner-drilled wells for the Moranbah project in many years,” QPM chief executive officer David Wrench said.
“We are excited at the increase in production these wells will deliver, which will provide a significant step change in the business for QPM Energy.”
The planned Teviot Brook South production wells are located in a highly productive area of the Moranbah gas project field.
The program schedule includes drilling all the vertical wells by the end of June and then the lateral wells from July to September.
QPM expects the wells to be completed, with pumps and surface equipment installed, commissioned and brought online progressively during the December quarter.
The company also has two workover rigs operating in the field.
When it acquired the Moranbah project last year there were 96 producing wells across the field.
QPM said its workover program had so far returned 22 wells to production increasing the producing well count to 118 wells.
It expects to have 130 wells in production by the end of May.
The total cost of the workover program and Teviot Brook South program is estimated at $27.5 million.
They are funded under the Dyno Nobel Development Funding Facility, provided to QPM Energy to fund the capital costs associated with increasing gas production.
he DFF has an initial aggregate limit of $80 million with an ability to increase to $120 million, if required.
This facility is to be repaid by the delivery of gas over the term of QPM Energy’s gas supply agreement with Dyno Nobel.
Image at top of page: Lucas Rig DRS 118 on location at TB118V1.