Wet wipes 11 per cent off Rio Tinto bauxite output
Above-average rainfall at Weipa knocked production from Rio Tinto’s bauxite operations down 11 per cent in the first quarter of this year compared to 2022.
The Weipa operations suffered reduced pit access, speed limits for mobile equipment and stockpile bottlenecks due to port closures, the company said.
Production was further affected by equipment downtime at both Weipa and Gove.
“Weather-related port closures at Weipa had a disproportionate impact on our third-party shipments. We
shipped 7.9 million tonnes of bauxite to third parties in the first quarter, 22 per cent lower than the same period of
2022,” the company stated.
Despite the drop to 12.1 million tonnes produced at Weipa and Gove for the first quarter, Rio Tinto has maintained its annual bauxite production guidance at 54 to 57 million tonnes.
The company said it was implementing plans to recover lost production at both sites through the remainder of the year.
Alumina production across the group of 1.9 million tonnes was 2 per cent lower than the first quarter of 2022 following unplanned outages at Queensland Alumina Limited (QAL) and plant reliability issues at Yarwun, in the Gladstone region.