Ball mill build on a roll at Ravenswood Gold
Construction of a new ball mill as part of the major Ravenswood Gold expansion is well underway, with completion due in May.
Ausenco, WDC (Western Downs Contracting), M2P, Sun Engineering and Minelec are among the contractors working on the project at the North Queensland gold mine.
A Ravenswood Gold spokeswoman said the concrete work was 75 per cent complete and the overall mill build about 16 per cent complete.
This fourth mill at the site will increase Ravenswood Gold milling capacity from 5 million tonnes per annum to 7.2Mtpa.
The mill construction commenced with a single pour of more. . .