Study provides firm foundation for Dianne start

Revolver Resources (ASX:RRR) says detailed technical and engineering work shows a strong business case for its Dianne copper mine project, with a forecast pre-tax free cashflow of more than $125 million.

The study results provide a confident foundation to wrap up funding arrangements and begin construction activities, according to Revolver managing director Pat Williams.

The Far North Queensland copper operation is expected to cost $19.7 million to bring online and would produce about 14.3kt grade-A copper cathode over a four-year period of production.

“The full suite of relevant technical work completed over a two-year period has identified a compelling commercial outcome from the near-surface, continuous Dianne deposit – which demonstrates excellent amenability to leaching and SX-EW processing in order to produce LME copper cathode from onsite facilities,” Mr Williams said.

Discovery Parks Banner

“A series of robust input assumptions have been used within the study, delivering a strong result from both a commercial and risk perspective.

“With a range of additional deposit extension opportunities available proximate to the planned open pit operations, further upside potential clearly also remains.”

The project is centred on the historical Dianne copper mine, about 265km north-west of Cairns, and is located entirely within granted mining leases.

An updated mineral resource estimate released in November 2025 indicates a total of 18,000 tonnes of contained copper.

Mining it would involve a small-scale operation based on contractor open-pit mining and processing activities. The site is expected to employ a workforce of up to 35 personnel on a multi-shift roster at maximum capacity.

The mining schedule indicates that mining will occur in a single stage pit over about three years to produce about 1655kt of ore feed to be delivered to the crusher and heap leach pad at an average strip ratio of 1.4:1.

Revolver views the Dianne project as offering a near-term, strategic opportunity to generate cashflow to pursue broader company growth initiatives.

This includes further exploration at Dianne and at Revolver’s Osprey copper project, about 220km north of Mount Isa.