Study outlines 26-year Sandy Mitchell operation

An updated scoping study for the Sandy Mitchell rare earths and heavy minerals project outlines a 13.0Mtpa mineral sands operation over a mine life of about 26 years.

The Far North Queensland project would cost $383.6 million to bring online, including a 25 per cent contingency, and deliver average annual revenue of about $348 million, proponent Ark Mines said.

It would run as a conventional mineral sands operation with dozer-push mining, wet concentration, flotation and a mineral separation plant producing a rare earth mineral concentrate (monazite and xenotime), zircon, titanium minerals, garnet and mica products.

“Sandy Mitchell has the scale to support long-life, scalable production of both light and heavy rare earths, alongside zircon, garnet and mica,” Ark Mines managing director Ben Emery (pictured right) said.

“On our review it is the largest rare earth resource of its type reported under the JORC Code, and this study shows it can support a 26-year operation with a post-tax NPV of $883 million. (The resource covers less than 22 per cent of the radiometric high area on our tenement).

“This is simple sand mining. The ore is free-dig from surface, with no drilling or blasting, and tailings go back into the mined area so the land can be progressively rehabilitated.

“That gives us a low operating cost of $8.31 per tonne of ore.

“It is an operation designed to keep its environmental footprint small, in an established mining region where we already hold a granted mining lease.

“We have strong support from the Queensland Government, and potential offtake partners have shown real interest in our products and have been waiting for this study.

“Our next step is the pre-feasibility study and bulk sampling, which will take Sandy Mitchell towards a development decision and production.”

MEC Mining prepared the scoping study with input from IHC Mining, Mineral Technologies and Ark Mines.

It was based on the mineral resource estimate announced on September 22 of 379.4 Mt at 5430ppm monazite equivalent (97 per cent measured and indicated).

The Sandy Mitchell project is located on Mount Mulgrave Station, about 230km north-west of Cairns and 200km north-north-west of Chillagoe.