Study highlights Mount Mackenzie gold mine potential

A scoping study shows a strong case for the development of an open-cut gold mine at Mount Mackenzie in Central Queensland, Resources and Energy Group says.

The company was granted a mineral development licence last month for the entire Mount Mackenzie mineral resource and all land required for the project’s development.

Resources and Energy Group said today the scoping study identified a 300,000-tonnes-per-annum open-cut development with on-site gold plant as the best case to progress.

The project, about 150km north-west of Rockhampton, would cost about $13 million to bring online.

“The outcomes of the scoping study based on the recently optimised mineral resource for the Mount Mackenzie gold project indicate the potential for development of a low-cost and profitable project,” chief executive officer David Frances said.

“The study concludes that a mine lief of about four years with production of 45,000 oz gold would provide an attractive payback period of approximately 15 months based on an initial capital cost of approximately $13 million.

“The study has also identified a potential mining and process route which would enable recovery of a greater proportion of the primary mineral resources than presently contemplated.”

Mr Frances said the feasibility study for Mount Mackenzie and exploration potential in the immediate vicinity were company priorities.

https://www.i-q.net.au/main/little-duke-adds-to-big-gold-picture-for-ausmex
https://www.i-q.net.au/main/impact-pulls-out-of-clermont-gold-project

Share Post:

Share Post:

3
You have FREE views remaining
×