Stanmore brings on extra fleets at former BMC sites
New owner Stanmore Resources is introducing additional excavator fleets at the South Walker Creek and Poitrel coal mines in the Bowen Basin.
The seventh fleet at South Walker Creek, 35km west of Nebo, will run under a wet hire contracted arrangement and is expected to be operational from early next year.
It was approved to advance stripping activities and de-risk coal flows ahead of a major 70-day shutdown of dragline 27 for maintenance and conversion from DC to AC in 2024.
Poitrel’s seventh fleet is expected to be introduced as a dry hire arrangement where the mine will hire and train operators with support from its New to Industry program with the ramp up of operations from the final quarter of this year.
Stanmore in August announced a deal with Mitsui to see it take 100 per cent ownership South Walker Creek and Poitrel, as well as Wards Well and other projects in the Bowen Basin.
This followed its $1.8 billion buyout of mining giant BHP’s 80 per cent stake in the group, now known as Stanmore SMC.
In its latest quarterly report, Stanmore said record combined dragline movement in August of 2.9Mbcm (from two draglines) and explosives loading performance had supported an accelerated overburden stripping program at South Walker Creek.
Excess pit water delayed activity early in the quarter, which resulted in lower than expected feed coal quality and yields in August. Operations normalised last month, when 588Kt of coal was produced from the CHPP.
The site produced 1.5Mt saleable coal in the September quarter, while Poitrel produced 1.1Mt.
Related: Action Drill and Blast wins $65m coal contract
Strong truck and shovel performance, record total stripping in June 2022 and improved 600t excavator dig rates led to record coal mining volumes at Poitrel – 35km east of Moranbah – in August.
The gains were partly offset by wet weather across the Bowen Basin in early July and early September, Stanmore said.
“July saw the commencement of mining and processing of two seams previously deemed unviable at very low
incremental strip ratios – Vermont 2/3 (V23) and Vermont Lower (VL) to take benefit of the available capacity at
the Red Mountain CHPP, which together contributed 317Kt of Run of Mine coal to overall production,” the company reported.
“Processing of these seams achieved acceptable yields and the coal quality outcomes will now form part of Poitrel’s standard product mix.
“Yields improved against forecast for the quarter with a focus on accelerating high-quality feed sources.”