September quarter shines for AIC Mines

AIC Mines is emerging from a cracking quarter – seeing the first stope fired at the new Jericho mine, launching into commissioning for the expanded Eloise processing plant, and inking a deal to acquire the Mount Cuthbert copper project.

The company also clocked up a record quarterly net mine cash flow of $33.4 million from its operations for the three months ending September 30 after capital investment of $7.9 million.

Chairman Aaron Colleran described it as a quarter where AIC Mines (ASX: A1M) set itself up for short-term, medium-term and long-term success.

Main image: Commissioning is underway on the expanded Eloise processing plant, pictured at night.

Eloise and the fledgeling Jericho operation produced 3072t of copper and 1562oz of gold in concentrate between them for the quarter as AIC sets its sights on achieving commercial production rates out of Jericho as soon as January 2027.

The quarterly net mine cash flow of $33.4 million beat the company’s previous record, set in the March quarter, by $5.7 million, aided by an increase in copper sales and a strong metal price environment.

AIC is maintaining its full-year guidance of 17,500-18,500t of copper and 7250-7750oz of gold in concentrate at an AISC of $4.80/lb-$5.20/lb and AIC of $5.20/lb-$5.60/lb.

Production for the September quarter was below guidance due to delayed access to higher-grade material in the Eloise Deeps and Lens 6 deposits, and earlier than planned processing plant shutdowns for cutover work to connect new equipment, the company said.

‘A seismic event in the fresh air drive on the z330 Level (Deeps current mining level is z405 Level) occurred late in the quarter and required rehabilitation of local ground support and escapeway before the Deeps and Lens 6 stopes could be safely accessed,’ it reported. ‘This rehabilitation work has subsequently been completed and full access has been re-established.’

The first production stope on 4975 Level (215m below surface) from Jolly shoot at Jericho.

The ore production shortfall from Eloise Deeps and Lens 6 was made up by early access to Jericho development ore.

The first production stope there was fired at the Jolly shoot on September 24, about two weeks ahead of schedule. The ramp-up to initial production rates of about 37,000tpm from Jericho is underway.

Meanwhile, the company said EPC contractor GR Engineering Services had made significant progress on the expanded 1.1Mtpa Eloise processing plant expansion during the quarter, with construction effectively complete.

‘AIC Mines now has two commissioning metallurgists and a commissioning superintendent onboard to assist with the commissioning and ramp-up, and to ensure a smooth transition from the construction team to the operations team,’ it reported.

During the quarter, AIC Mines entered into binding agreements to acquire Materra Metals, owner of the Mount Cuthbert copper project, for $120 million (consisting of $100 million in shares and $20 million in cash).

It also entered into a subscription agreement with existing major shareholder Hawke’s Point Resource Finance and its affiliates for $70 million worth of shares.

An extraordinary general meeting will be held in Perth on November 4 to seek shareholder approval for the acquisition and placement.