Sedgman to carry out Jellinbah plant upgrade
Sedgman has been awarded a contract to deliver an upgraded coal handling and processing plant for the Jellinbah mine, north of Blackwater in Central Queensland.
Sedgman commenced the feasibility study for the plant upgrade in February this year, continuing into front-end engineering design phases and an EPC offer provided to Jellinbah Group in June.
The expansion of the processing plant will increase its capacity from 285 tonnes per hour to 500 tonnes per hour.
In a statement on the contract win, Sedgman said detailed engineering and procurement were now underway.
The project team will mobilise to site in March 2021 to complete the installation, with commissioning towards the end of the year.

Sedgman has a long history of working with the Jellinbah Group, which also owns the Lake Vermont Mine where Sedgman has successfully delivered several major projects.
The business also recently completed commissioning for the Stage 2 CHPP at QCoal’s Byerwen site.
It said the finalisation of Stage 2 was the latest in a series of contracts at the Byerwen mine, beginning in early 2018 with the stockpile and train load-out, followed by the Stage 1 CHPP engineering, procurement and construction, and the operations and maintenance contract ongoing since later that year.