Savannah’s Georgetown gold production on a roll
Savannah Goldfields (ASX:SVG) poured doré weighing 6.951kg yesterday after the recent resumption of gold production at the Georgetown processing plant in Far North Queensland.
Processing resumed in the first week of November, with feed comprising various blends of stockpiled Agate Creek material and Georgetown tailings.
The company poured gold doré weighing about 1.5kg back then and mint outturn certificates have since confirmed refined weights of 24.836oz gold and 20.326oz silver.
Related: Savannah resumes gold production at Georgetown
It said weekly doré pours were planned going forward.

Since milling operations commenced in November, gold had been accumulating on carbon within the gold plant and a regular elution cycle had now been established to recover gold from carbon to produce doré, Savannah said.
Meanwhile mining equipment has been mobilised to the Big Reef site ahead of the start of mining during this month.
A small open pit is planned to extend the historical Big Reef mine along strike, and the mining of that pit is planned to deliver up to 18,000 tonnes of inferred mineral resource to the Georgetown plant for processing.
Resumption of mining at Agate Creek and processing of Agate Creek ore is planned to commence in the second quarter of 2026 following the expected receipt of the updated environmental authority.
Savannah Goldfields also said it was continuing discussions with multiple small-scale gold producers in the Georgetown area with potential to scale up their operations and an interest in potentially toll treating their material at its processing plant.