Restart study underway for troubled 29Metals mine
29Metals has launched a definitive feasibility study to return its Capricorn Copper operation to production, with planned completion by the end of 2026.
The company outlined the progress in its latest quarterly report, noting that it achieved a sufficient reduction in surface water levels at the North-West Queensland site to bring the operation back online.
Government approval for a new long-term tailings storage facility (TSF3) was now the critical path imperative for a restart of production, it said.
Operations were suspended in March 2024 after an extended period of rainfall resulting in a steady accumulation of water within the mine’s regulated water storage structures. The site had still been clawing back from the impact of a deluge in 2023 when that happened.
The company said today that the total water inventory at Capricorn Copper was now substantially below the maximum operating level and surface water was now at levels similar to those before the extreme weather event in 2023.
“Excellent progress on water inventory reductions at Capricorn Copper means that water levels are no longer an impediment to a restart of production,” 29Metals chief executive officer James Palmer said.
“A production restart decision is now pending regulatory approval of our application for a new tailings storage facility, with the team on track to submit a response to a request for information from the regulator in the September quarter of this year.”
State approval of the TSF3 development is subject to an Environment Protection and Biodiversity Conservation Act referral process and the RFI response.
29Metals said it was considering a range of strategic options to source Capricorn Copper restart capital.