QMRS inspections pave way for Grosvenor return
Anglo American expects to have teams beginning the re-entry to the Grosvenor underground coal mine next week in the wake of Queensland Mines Rescue Service inspections.
The Grosvenor operation has been out of action since the workforce was evacuated on June 29 last year when a fire broke out underground after coal gas ignited.
Grosvenor mine general manager Shane McDowall said the operation had received approval from Queensland’s safety regulator for the first stage of re-entry – a significant milestone in the restart journey.
“This approval marks the beginning of a staged and carefully managed re-entry process, following the successful completion of key safety preparations last week, including initial mine re-ventilation activities,” he said.
Once QMRS preliminary reconnaissance inspections were complete, the company’s teams would begin their re-entry to Grosvenor, he said.
Related: Anglo poised for Grosvenor coal mine re-entry
“Every stage will progress in close collaboration with Resources Safety and Health Queensland and Industry Safety and Health Representatives, with the safety of our people our highest priority – always,” Mr McDowall said.
“Our crews have stepped up in amazing ways – solving problems, adapting technology in innovative ways, and rethinking how we do things underground.
“That team spirit – people from different backgrounds coming together – has been at the heart of our progress here at Grosvenor.”
An RSHQ spokeswoman said working on a safe path to re-entry for Grosvenor had involved several complex issues that required investigation.
“On August 5, an RSHQ inspector gave consent for the first stage of re-entry to commence on August 6,” she said. “All mining operations remain suspended for the time being.”
Anglo reported a 46 per cent drop in production across its steelmaking coal assets in Queensland for the half-year ended June 30 compared to the same time in 2024.
Related: Anglo wraps up divestment of Jellinbah stake
This reflected the suspension of mining at Grosvenor during the first six months of this year as well as the sale of its 33.33 per cent stake in Jellinbah.
Production was also impacted by the suspension of operations at Moranbah North after an underground incident on March 31.
The company reported an underlying EBITDA loss of $149 million for the half year (compared to a $592 million gain for the same time last year).