No federal changes needed over coal emissions case says Hunter MP
A New South Wales legal requirement is at the centre of a High Court decision on emissions and Mount Pleasant coal mine extension plans, and there is no need to rethink federal laws, according to Member for Hunter Dan Repacholi.
He was commenting after the court on Wednesday rejected an appeal by MACH Energy over a ruling that blocked state approval of a 22-year extension to the Hunter Valley operation on the grounds that the impact of greenhouse gases from coal exported from the operation had not been properly considered.
In a 3-2 High Court decision, the majority of judges found the NSW Independent Planning Commission had failed a legal obligation to impose conditions to minimise “to the greatest extent practicable” the impact of downstream or scope 3 carbon emissions.
Minerals Council of Australia chief executive officer Tania Constable today said the result was sending a shiver down the spine of all mining companies and projects not only in New South Wales but across Australia.
Mr Repacholi said the case was about a NSW planning decision under NSW law.

“The ball is now in the NSW Government’s court to explain how it will deal with the decision and give people a clear path forward,” he said.
“I’ve spoken with the Mining and Energy Union and others who are working with the company and the NSW Government to resolve this.
“Federal Environment Minister Murray Watt has made clear that the NSW legal requirement at the centre of this case does not exist in federal environmental law. This decision does not change federal law, and his advice is that no federal law change is needed.
“As the local member, I want this cleared up as soon as possible.”
Speaking in News24 this morning, Ms Constable said scope 3 emissions should be explicitly removed from the New South Wales law and not taken into account at any government level across Australia.
She said the MCA was very concerned that investment in Australia could be affected by the High Court decision.
NSW Natural Resources Minister Courtney Houssos said the government would carefully consider the full judgement, stressing that Mount Pleasant retains a separate approval to continue operating until 2032.
“The Minns Labor Government’s NSW Coal Industry 2026–2050 policy provides a clear framework for the industry. It supports important coal mining jobs that sustain so many of our regional communities, while charting a course to net zero,” she said.
“We have also made significant planning reforms. The recent approval of the Hunter Valley Operations project included detailed consideration of Scope 3 emissions and conditions to minimise them.
“We believe the current planning framework is capable of addressing these issues, and we’ll carefully examine the judgement to ensure future decisions meet the requirements of the law.
“MACH Energy has indicated it will continue to pursue options for the project, and we will engage closely with the company as it does so.”