Mount Mackenzie shapes up well for QMines strategy

QMines has demonstrated that its newly acquired Mount Mackenzie site can be economically mined via open pit mining, with ore to be hauled to the planned Mount Chalmers processing plant.

The positive open pit optimisation results mean the gold-silver project will be integrated into an updated prefeasibility study for the broader Mount Chalmers project, due for release in 2026.

QMines plans to develop a centralised processing hub at Mount Chalmers, 17km north-east of Rockhampton, supported by resources from its Mount Mackenzie, Mount Chalmers and Develin Creek projects.

Mount Mackenzie materially increases the scale of the enterprise, which is now underpinned by a mineral resource estimate of about 19Mt across the three projects.

It comes amid high gold prices, driven by central bank demand and global macroeconomic uncertainty, while silver has surged on the back of industrial demand from solar energy, electronics, and green technologies.

“We are delighted with this optimisation result at Mount Mackenzie, which confirms our newest asset to be a high-quality, high-margin open pit operation in the making,” QMines executive chairman Andrew Sparke said.

“For our shareholders, this means Mount Mackenzie could deliver significant low-cost ounces into our production profile.

“These results bolster our hub-and-spoke strategy, with Mount Mackenzie’s material contributing to a planned centralised 2.0Mtpa processing plant. We now have three advanced deposits… shaping up to be one of Australia’s next long-life, multi-asset copper and gold operations with scale.”

Key Mount Mackenzie optimisation points:

  • Production target: 800,000t of oxide and 1.5Mt of sulphide material
  • Combined open pit strip ratio of 4.2:1
  • Estimated in-pit metal: 100,000 oz gold, 658,000 oz silver
  • 90 per cent indicated resource, 10 per cent inferred resource
  • Metallurgically compatible with Mount Chalmers processing flowsheet

QMines completed its acquisition of the Mount Mackenzie project early this month in a $2.485 million deal with Resources & Energy Group.

The project’s mineral resource stands at 3.35Mt at 1.40g/t gold and 8.4g/t silver, comprising 151,000 oz of gold and 902,000 oz of silver.

QMines said the resource remained open along strike and at depth, offering clear growth potential.