Meandu life extension project advances through approvals
Stanwell Corporation’s proposed King 2 East project at the Meandu coal mine, 25km south-east of Kingaroy, is now open for public comment as it moves through the federal approvals process.
The Meandu mine supplies thermal coal to Stanwell’s nearby Tarong and Tarong North power stations, and the K2E project is proposed to allow it to continue to feed those plants for about another decade.
The proposed action is a ‘controlled action’ under the Environment Protection and Biodiversity Conservation Act and public submissions are open until close of business on September 17 as part of the assessment process.
The project will extend the Meandu mining area by 186ha to allow for the progression of the K2E pit to the east and associated infrastructure. This is an increase of about seven per cent on the existing approved surface rights area, according to project documents.
The Meandu operation includes a CHPP and multiple pits with capacity to supply the power stations with up to 7Mtpa of product coal. It has environmental authority to extract up to 11Mtpa ROM coal.
Related: BUMA snags contract extension at Meandu mine
The addition of the King 2 East area will not incease the annual production rates.
The combined Tarong power stations have a generation capacity of more than 1800MW and supply about 20 per cent of Queensland’s energy needs.
Supporting documents indicate the K2E project footprint has been minimised by matching the additional coal resources to the incremental quantity of fuel required to supply the Tarong power stations for their remaining life.
The current projected date for the withdrawal of the Tarong power stations (pictured below) from the National Electricity Market is between 2036 and 2037.

Stanwell – which owns Meandu through its TEC Coal subsidiary – considered a number of options to ensure a continued cost-effective and reliable coal supply to the plants.
It identified the K2E project as the best fuel source option to provide guaranteed fuel supply to the Tarong power stations from 2026 to end of life.
Alternatives included the development of the Kunioon deposit, about 14km north north-west of the Meandu mine, which is also held by TEC Coal.
Until 2008, the intention was to transition mining operations from Meandu to Kunioon by 2011, but an evaluation identified more economic coal available at Meandu than had been assumed.
Related: $70m overhaul kicks off at Tarong North plant
Stanwell said the capital cost and disturbance footprint together with other risks associated with opening a new coal mine made this option less favourable than the K2E project.
Use of the Glen Wilga deposit, about 150km west of the Tarong power stations, has also been weighed up and dismissed, paperwork for the K2E extension shows.
Below: The K2E area (black outline) shown on a map of the Meandu mine site and Tarong power plants.