A major overhaul project has kicked off at the Tarong power stations complex, south-east of Kingaroy, involving a workforce of 550. Tarong power stations site manager Wayne Martyn said the Unit 1 shutdown project would run for 50 days and include 14,500 activities. “The overhaul attracts contractors to fill a range of roles including welding […]