Longwall changes planned to tackle Centurion challenges
Geological challenges have driven Peabody Energy to tweak its longwall set-up at the Centurion mine near Moranbah, with an expected price tag of up to about $17 million ($US12 million) for the changes.
The company – which owns coal mines in the United States and Australia – detailed the move in its September quarter report.
Peabody globally reported adjusted EBITDA of almost $140 million ($US97.5 million) in the third quarter of 2026 compared to about $142 million ($US99.5 million) in the prior-year quarter.
Its Centurion mine, which began longwall production in February this year, achieved its targeted third quarter sales volume – shipping 0.58 million tons – while working through continued geological challenges, the company said.
Related: State backs Centurion power plant expansion
“The third quarter demonstrated improving momentum across the portfolio with all segments reporting positive adjusted EBITDA, while our seaborne operations benefited from higher pricing,” Peabody Energy president and chief executive officer Jim Grech said.

“During the quarter, we worked through higher-cost faulted conditions at Centurion, which slowed advance rates, although the mine still reached its third quarter sales targets.
“Looking ahead to the fourth quarter, our priorities remain operating safely, clearing the faulted zone at Centurion, and improving free cash flow as seaborne markets remain strong.”
The Centurion longwall encountered more problematic faulting than anticipated across multiple areas of the panel late in the last quarter.
‘Increased geological complexity impacted longwall performance in October, with production of approximately 45,000 tons for the month, and the company expects fourth quarter sales volume between 0.3 and 0.5 million tons,’ Peabody said in the update.
‘The company now has a clearer understanding of how the current longwall configuration performs in these conditions and has identified targeted engineering modifications.’
These include a base-lift power increase, at an estimated cost of up to $2.85 million ($US1.5 to $US2 million), to be completed during scheduled maintenance in the current panel.
A two-stage flipper is set to be installed during the next longwall move, now expected in the third quarter of 2027. This is expected to cost $US5 to $US10 million – which is about $7 million to just over $14 million in Australian dollars.
The company has lowered full-year guidance for metallurgical coal out of Australia by 0.6 million tons and costs are expected to increase by about $15 per ton, primarily due to lower Centurion production.