Revolver Resources has lined up a $3 million loan to back the next phase of early works construction and procurement activity for the Dianne copper mine in Far North Queensland.

The company said this would increase the momentum of activity leading towards a quick construction and commissioning program aimed at delivering copper cathode within 12 months of the project’s final investment decision.

At the same time, it is advancing funding package negotiations for the $20 million required to bring the planned mine online as well as expected working capital requirements of about $10 million.

‘Targeted completion of a fulsome project funding package is scheduled to be followed promptly by final investment decision,’ the company said in an update to the ASX

‘Following this, residual contractor and equipment mobilisation is scheduled to take place, with commencement of full-scale construction shortly thereafter.’

Revolver Resources (ASX: RRR) has executed binding documentation for the $3 million development works bridge loan facility with BBPRI (Blackbird).

It will cover expenses such as key civil works, completing the SX/EW plant design and long-lead item procurement activities.

The loan has a six-month term, with repayment of $3.7 million (principal, capitalised interest and fees) at maturity.

Revolver’s Dianne project is located about 260km north-west of Cairns and in 2024 attracted the first Queensland Critical Minerals and Battery Technology Fund grant (securing $1.3 million).

Mining it would involve a small-scale operation based on contractor open-pit mining and processing activities. The site is expected to employ a workforce of up to 35 personnel on a multi-shift roster at maximum capacity.

The company announced in May that Cape York business CEMACC would carry out the civil earthworks needed to bring the Dianne copper mine project into production.

CEMACC will transition into the provision of mining, crushing and leach pad loading services for Dianne operations

The operation is expected to produce about 14.5kt copper over an initial four-year operating life.