Insurance hurdle, impairment woes for 29Metals
29Metals is at odds with insurers over coverage for underground loss and damage stemming from the extreme weather event at the Capricorn Copper mine, 120km north of Mount Isa, in March.
Meanwhile the miner is undertaking an assessment of carrying values for its half-year financial results, noting a sustained decline in its market capitalisation due to the post-flooding suspension of operations at Capricorn Copper.
“While work has not been finalised, including completion of the external auditor’s review, 29Metals expects that the HY2023 Results will include total non-cash impairments relating to Capricorn Copper in the range of $180- $210 million,” 29Metals stated.
Operations at the North-West Queensland site were suspended after about 500mm of rain fell at Capricorn Copper over seven days in early March, including more than 200mm on the evening of March 7.
Capricorn Copper restarted mining operations in the Mammoth and Greenstone areas of the operation this month in a phased recovery plan.
Mining is not expected to resume at the Esperanza South sub-level cave mine until the first half of next year.
Insurers have coughed up $24 million so far for damage to property on the surface and associated business interruption, with the claim process for that aspect is ongoing.
“In relation to underground loss and damage, based on 29Metals’ preliminary claim submission and information provided to date, insurers’ have taken the position that the policy does not respond,” the company reported to the ASX today.
“Further information has been requested. 29Metals does not agree with the insurers’ position regarding coverage of the underground loss and will continue to work with insurers in relation to the further information required to advance this claim.”