George Fisher doubles down on raiseboring
Contractors Pybar and RUC are carrying out two simultaneous raiseboring projects at Glencore’s George Fisher mine to boost ventilation underground and sustain the southern blocks of its L72 operations.
The works will see the addition of a new fresh air intake and return air shaft, both stretching 750m from the surface to underground and each with a diameter of 5m.
Senior project engineer Robert Harrington said running two raiseboring contractors meant operation had access to more specialised equipment.
“This will save about 18-months on the project schedule and provides the best overall return on investment,” he said.
Prior to commencing raiseboring, the team completed 90m of ground improvements.
“The design for the ground improvements was technically challenging, but the execution phase allowed us to increase the diameter of the planned raises and completely eliminated the need for an additional fresh air intake in the long-term,” Mr Harrington said.

Drilling conditions within the upper stratum of the shaft have provided a challenge due to water loss.
“Because raiseboring uses a rotary mud drilling process, with water injection playing a critical role, water is sometimes lost through fractures resulting in delays,” Mr Harrington said.
George Fisher mine manager Rebecca Roper said the additional ventilation was required to ensure continued safe mining extraction as the operation advanced into new areas of the L72 underground footprint.
The raiseboring is expected to be completed by June.
Related: Mount Isa Mines confirms key roster change
A cone will be installed over the fresh air intake to direct fresh air down to the active underground headings, while fans will be added to the return air shaft to facilitate the exhaust of contaminated air from underground.
The second phase is due to be completed in the third quarter, with the commissioning of the fans and other surface infrastructure, and the final phase is scheduled for early 2023.
In the final stage, there will be further drilling to connect the base of the surface shaft (12-level) with the base of the mine (18-level).