Genex marks progress as Kidston works push on
Genex Power has outlined its latest progress on the Kidston pumped storage hydro project including major underground works as it heads towards energisation in the second half of next year.
Key work at the North Queensland site in the past quarter focused on the continued excavation of the Main Access Tunnel (MAT), the power station cavern and supporting construction adits, Genex chief executive officer James Harding said.
“We have also now completed two of the four vertical shafts by raiseboring and have commenced works on the first of the water intake shafts; while the Wises Dam works continue with final preparation works being undertaken and commencement of placement of the dam liner,” he said.
The next three months are expected to see:
– Continuation of excavation of the underground works including the power station cavern, MAT, transformer caverns, and associated underground construction adits;
– Completion of the Wises Dam and commencement of Stage 2 dewatering operations;
– Completion of the internal lining for the cable shaft;
– Completion of the raiseboring operations for the two intake shafts, in turn allowing concrete lining works to commence;
– Continued progression of clearing and access works for the transmission line and tower foundations from Kidston to Guybal Munjan and commencement of the erection of the lattice towers;
– Completion of the K2-Hydro switchyard and internal transmission line between K2H and Aurumfield switchyards; and
– Delivery onsite of the electromechanical equipment by Andritz Hydro.
The June quarter saw Genex celebrate a milestone with the energisation of its first battery energy storage project at Bouldercombe, Rockhampton.
Related: Genex flips the switch on CQ battery project
Mr Harding said the fact that this was completed on time and within budget was a testament to the strength of the Genex Power team and contractors Tesla, Consolidated Power Projects and Powerlink.
“We are eagerly looking forward to the full operation of the Bouldercombe Battery Project ahead of the peak summer period,” he said.
The company had also continued to progress its pipeline of development opportunities, including the Kidston Stage 3 wind project and the Bulli Creek battery and solar project.
Image at top of page: Power station cavern excavation advances at the Kidston pumped storage hydro project.