Foxleigh seeks Pipeline Pit extension
An expansion plan for the Foxleigh coal mine’s Pipeline Pit has hit an approvals milestone, with its referral under federal environmental laws now open for public comment.
The proposal includes a minor extension of the existing Pipeline Pit (about 100m wide and 400m long), construction of a flood protection landform, construction of a waste rock dump and supporting infrastructure including the realignment of a 605mm clean water pipeline that supplies neighbouring coal mining operations.
The existing Foxleigh operation, about 12km south-east of Middlemount, is a conventional open-cut mine which produces about 3.5Mtpa of premium low volatile pulverised coal injection (LV PCI) metallurgical coal.
In paperwork for the EPBC Act approval, the proponent said the Pipeline Pit as a whole – including the expansion area to be considered – was scheduled to produce about 6.1Mt of run-of-mine (ROM) coal and about 57.6 million bank cubic metres (Mbcm) of prime waste.
Waste removal is set to commence in 2027 and coal production between 2031 and 2041.
Coal production from the Pipeline Pit would represent 4 to 28 per cent of the Foxleigh mine’s annual ROM coal production in the years in which it was mined, and extended the life of the mine by about 1.5 years at 4Mtpa, according to the documents.
The portion of the pit within the relevant project area accounts for about 0.08Mt of ROM coal, representing less than 1 per cent of the Foxleigh mine’s annual ROM coal production.
The proposed Pipeline Pit extension is separate from the Roper Creek extension project (EPBC referral 2026/10683), which is also moving through the federal environmental approvals process.