Foxleigh mine extension plans advancing
The owners of the Foxleigh coal mine, 12km south-east of Middlemount, are advancing a proposal that would help keep it ticking along steadily until about 2052.
Public comment is now open on the Roper Creek extension project’s referral for federal environmental approval.
The Foxleigh open-cut operation, established in 1999, produces about 3.5Mtpa of low volatile pulverised coal injection (LV PCI) metallurgical coal.
The Roper Creek extension project involves developing one new satellite open cut pit and extending the existing Eagles Nest pit.
Documents supporting the development say it would allow about 18Mt of run-of-mine (ROM) coal to be mined from the relevant area over a 20-year period using the same conventional truck and excavation processes, fleet and workforce used elsewhere at the mine.
The development of the satellite open-cut area will be timed to come online as production from other parts of the existing operation declines, maintaining production to meet market demand.
The operational workforce is expected to be unchanged from the existing Foxleigh mine operation, at about 770 personnel.
The paperwork for the Roper Creek extension project shows that a separate Environment Protection and Biodiversity Conservation Act referral is being prepared for an extension of the Foxleigh mine’s Pipeline Pit.
The Roper Creek extension project will require new access, haul roads and satellite crib facilities. A flood protection landform will be constructed to protect the open-cut pits from flooding.
Other elements necessary to support mining operations to be developed in the Project area will include:
- separate vegetation and topsoil stockpile areas
- out of pit and in-pit overburden dumps to be stabilised in accordance with the relevant Environmental Authority requirements
- a run of mine (ROM) pad for temporary storage of coal from the Roper Creek pit
- and water management infrastructure, including pipelines, dams and drains to collect and manage mine-affected water, sediment water and clean water.
Developing the Roper Creek pit will require relocating Barwon Park-Middlemount R to the north of the pit. The proponents say the location of the road realignment will be selected pending the outcome of discussions with Isaac Regional Council.
QMetco acquired the Foxleigh mine in August 2016 via its ownership of Middlemount South, which purchased Anglo American’s 70 per cent interest in the Foxleigh joint venture.
The mine is owned and operated as a joint venture by Middlemount South with POSCO Australia and Nippon Steel Australia (owning 20 per cent and 10 per cent respectively). POSCO and Nippon are longstanding customers of Foxleigh.