Deep and meaningful intercepts at Ernest Henry

Evolution Mining has intersected mineralisation as far as 900m below the current mining area at Ernest Henry, boosting faith in the site’s longevity, according to managing director and chief executive officer Lawrie Conway

Intersections during recent exploration success included 61.3m at 1.26 copper and 0.77g/t gold, he told a briefing held to co-oincide with the release of the company’s latest quarterly report.

“It gives us confidence that Ernest Henry is likely to be operating well beyond the current mine plan to 2042,” Mr Conway said.

The Cloncurry district copper-gpd operation delivered record net mine cash flow of $186 million at a record low AISC (all-in sustaining cost) for the quarter.

Insurance proceeds benefited net mine cash flow by $24 million.

Higher gold and copper grades of 0.45g/t and 0.86 per cent, combined with processing recoveries of 80.6 per cent and 95.5 per cent, underpinned consistent gold and copper production of 17koz and 12kt respectively, the comopany reported.

The site’s Bert project advanced during the quarter with the primary mining contractor Redpath mobilised on site to commence underground mine development.

The project is designed to utilise latent mill capacity and underpins Ernest Henry’s longer-term production and cash flow profile.