‘Compelling economics’ for FNQ silica sand project
The prefeasibility study is out for Diatreme Resources’ flagship Northern Silica Project (NSP), demonstrating ‘compelling economics’ for an operation costing $443.5 million to bring online in its first phase.
Diatreme (ASX:DRX) chief executive officer Neil McIntyre said the study confirmed what the company had long known – that the NSP was a genuine world-class asset.
“The 3Mtpa Phase 1 start-up case, with a pre-tax NPV of $1.29 billion and a 36 per cent pre-tax IRR, delivered from a low-cost operation with a four-year payback, places NSP among the most compelling critical minerals developments in Australia,” he said.
“With our silica resource base and our joint venture with global material solutions leader Sibelco, we are exceptionally well positioned to move through the next steps including a definitive feasibility study (DFS) and then into development.”
The silica sand project would contribute enormous economic benefits to the local community of Hope Vale and Cooktown, he said.

“Diatreme has committed to a 50 per cent Indigenous employment target, and we are focused on maximising local employment and local business opportunities,” Mr McIntyre said.
“The operation will employ up to 214 during construction and 128 in operation, with a focus on local procurement and service providers, ensuring benefits stay where benefits belong in the project area.”
The Phase 1 start-up operations of 3Mtpa are modelled over an initial 25-year mine life and would deliver gross revenue of $8.1 billion and net revenue of $6 billion.
Phase 2 offers a potential expansion up to 5Mtpa from year three and would deliver pre-tax NPV of $2.4 billion from investing about $38.5 million of additional CAPEX.
It would deliver gross revenue of $13.1 billion over the life of mine and net revenue of $9.8 billion.
Diatreme chairman Brian Flannery described the prefeasibility study as a significant milestone for Diatreme and its shareholders.
“The scale and purity of our silica portfolio, combined with growing global demand for solar PV and specialty glass, gives us a rare opportunity to build an inter-generational, low-iron high purity silica business, with the Cape Flattery deposit one of the largest high purity silica sand deposits in the world,” he said.
“Together with our partner Sibelco and the support of the Queensland Government’s critical minerals agenda, we are focused on unlocking this value responsibly for the benefit of our shareholders and in close partnership with Traditional Owners and the local community.
“We have a genuine opportunity to build a project of national and international significance, and I am confident we have the right team in place to ensure success, building not only Diatreme’s future but contributing economically to the future of Far North Queensland and beyond.”
The NSP is a proposed greenfield open-cut high-purity silica sand mine located near existing export and port infrastructure within the Cape Flattery to Cape Bedford silica mineral province.
It boasts 633Mt of total mineral resources including a maiden ore reserve of 151m tonnes grading 99.25 per cent silicon dioxide for the Si2 deposit, underpinning an initial 25-year mine life.