Comet Ridge sets out Mahalo development plans
Comet Ridge has laid out its plans for the development of the Mahalo Gas Hub, targeting a final investment decision in mid-2027.
The company has sole ownership across the 1847sq km of Mahalo Gas Hub tenemnets after its acquisition of Santos’ 42.86 per cent interest in the Mahalo joint venture.

Comet Ridge said the optimised Mahalo Gas Hub project incorporated 2P and 3P Reserves from the Mahalo Gas Project (originally the JV), Mahalo North and Mahalo East into a logical, staged development plan.
It said it was targeting first gas to align with the Australian Energy Market Operator’s (AEMO) forecast need for new supply and the expiry of the initial terms of long-term supply agreements with the Gladstone LNG projects.
‘Mahalo is designed to deliver into both the export and the domestic systems and is planned to be producing when replacement volumes are required. Comet Ridge intends to be a long-term supplier to the Gladstone LNG projects,’ it said in an update to the ASX.
The planned development stages are:
- Stage 1A — Initial Development: Stage 1A is the basis for the final investment decision. It comprises about 50 well sets within the Mahalo Gas Project production licences (PL 1082 and PL 1083) and the Mahalo North production licence application area (PLA 1128), supplying an initial plant capacity of 50 TJ/d from three reciprocating compression units of approximately 17.5 TJ/d each. Tenure for PL 1082 and PL 1083 is in place and PLA 1128 is to be granted before a final investment decision.
- Stage 1B — Expand: Stage 1B plans to step plant capacity up to 70 TJ/d with the addition of a fourth compression unit and a similar number of additional well sets as Stage 1A across the Mahalo Gas Project. This stage effectively doubles the project area.
- Stage 1C — Extend: Stage 1C plans to develop the Mahalo Gas Hub’s current 2P Reserves, adding additional well sets in the north-west part of Mahalo North “Comet River” (PLA 1132) and Mahalo East (PLA 1179) following EPBC referral, while maintaining plant capacity at the expanded 70 TJ/d.
- Stage 2 — Full Field Development: Stage 2 considers development of existing 3P Reserves areas, stepping out from the Stage 1 development area. Depending on market requirements, this stage would either extend the production plateau at 70 TJ/d or expand compression further towards an increased pipeline capacity of up to 100 TJ/d, with appraisal and build-out during development informing the plan. A final stage will consider extending development into the Mahalo Gas Project’s contingent resource areas (within the existing PCA to the south) and deeper areas within the company’s tenure, informed by targeted appraisal and build-out during development.
With the Federal Government’s Domestic Gas Reservation Scheme likely to increase demand for third-party gas, Comet Ridge plans to target LNG projects at Gladstone in marketing the Mahalo gas.
The company said gas produced from three of the four Mahalo Gas Hub northern blocks was subject to Queensland domestic supply conditions.
Those conditions do not apply to PL 1082 and PL 1083, which together hold 266 PJ or 74 per cent of the hub’s 2P reserves, nor to the 2C contingent resources in PCA 338 for southerly expansion.
Gas subject to Queensland domestic supply obligations could still be acquired by an exporter and applied towards its domestic supply obligation, it said.
‘The timing of the Mahalo Gas Hub development coincides with a period in which a number of the long-dated supply arrangements underpinning those (Gladstone LNG) projects start to reach the end of their terms,’ the company said in an update to the ASX
‘In its announcement of June 29, 2026, Santos disclosed the execution of a gas sale agreement to supply 200 petajoules of gas to the South Australian Strategic Gas Reserve. The GSA is over 10 years, with 20 petajoules per annum delivered ex-Moomba and first gas on March 1, 2030.
‘This coincides with expiry of Santos’ Horizon contract with the GLNG joint venture, under which Cooper Basin gas has been supplied into the GLNG project. Replacement volumes will need to be contracted in advance of those expiries, and gas capable of delivery prior to 2030 is being sought accordingly.