Cloncurry sees signs of Eva copper mine progress
Engineering and construction company Bechtel has started work on a facility at the Cloncurry Industrial Estate to support the development of Harmony’s Eva copper mine.
The site will serve as the project’s main logistics, laydown and pre-assembly hub. Development works are expected to continue through to early September before the site becomes operational.
Harmony said crews would be clearing and preparing the land over the next two months, laying about 15,000 cubic metres of fill to create a heavy-duty hardstand and completing road, drainage and security fencing works across the site.
From mid-July, Harmony said buildings would begin taking shape, including a dome-shaped warehouse, temporary office, crib and amenities facilities for the workforce.
The development is expected to support economic activity in Cloncurry during construction, with about 40 to 50 tradespeople involved in delivering the works and opportunities for local suppliers and service providers to participate where available.
Harmony is targeting first production in 2028 from the $2.3 billion-plus Eva mine development, about 75km north-east of Cloncurry.
“Bechtel is proud to be delivering this facility in Cloncurry,” Bechtel site manager Nick Windust said.
“It’s a critical piece of the puzzle for Eva, and we’re looking forward to working alongside the local community as we bring this development to life over the coming months.”
Once the Eva process plant is commissioned, the facility will be handed over to Cloncurry Shire Council.
“Seeing work get underway at the Cloncurry Industrial Estate is a proud moment for the Eva copper mine project,” Harmony Australasia chief development officer Johannes Van Heerden said.
“This development demonstrates our commitment to delivering tangible, lasting benefits for Cloncurry and our local stakeholders.”