Skip to main content

© Industry Queensland. All rights reserved.

Designed by: Getmilk

Century mine ball mill back in business

The ball mill at Century zinc mine is back in action after an electrical failure in the motor during severe weather in January.

The processing operations at the lower Gulf site were switched into ball mill bypass mode in late January
due to the motor problem, linked to significant moisture ingress, New Century Resources said.

It returned to normal operations last week following repairs, and operations are now being ramped
back up.

New Century said the company’s spare rotable motor continued to undergo its scheduled refurbishment works and was expected back on site in late March / early April.

“In addition, a new custom-built, contemporary designed motor is on order and will become the duty unit upon arrival at the Century Mine later this year, ensuring the availability of multiple critical spares and greater long-term reliability from this area of the processing plant infrastructure,” New Century Resources said.

The company reconfirmed production guidance for the 2022 financial year of 110,000t to 130,000t of zinc metal at C1 costs of US$0.85/lb to US$0.95/lb on a payable metal basis.

New Century is a top-15 global zinc producer, operating Australia’s largest hydraulic mining operation at the Century site – where it processed zinc recovered from historical tailings.

The company is also progressing proposed in-situ mining projects at the Century mine and is exploring the potential to restart copper production at the Mount Lyell mine in Tasmania.