One of Queensland’s most successful copper explorers now has full ownership of all its copper projects and sees a clear path ahead to production.
Carnaby Resources (ASX:CNB) told the RIU Explorers Conference in Fremantle this week that it now had a total resource at its Greater Duchess discoveries of 20.2 million tonnes of 1.5 per cent copper equivalent for a contained 440,500 tonnes of copper equivalent.
Managing director Rob Watkins told delegates that a pre-feasibility study was being completed this quarter to define a maiden reserve.
Carnaby has a binding toll milling and offtake agreement to the north-west with Glencore, which retains its facilities at what is ranked as Australia’s copper processing capital.
Related: Latest Trek 1 results strengthen open-pit case
Mr Watkins said Greater Duchess retained enormous exploration upside from Carnaby’s discoveries made back in December 2021.
In the same regions, the now advancing Lady Fanny, Burk and Wills, Mount Hope and Mohawk deposits were exploration successes for the company, while the acquired Trekelano project (image at top of page) was now part of the development blueprint.

Trekelano operated from 1911 to 1943 and produced 188kt at 10.3 per cent copper and 2g/t gold and now has a 400m extension to the known high-grade lode. Carnaby expects an initial scoping study for development by late this year.
Mr Watkins said that the company saw a new frontier for discovery at the Magna Lynn Southern Corridor.
There were new targets for iron sulphide copper-gold in “magnetically quieter rocks”.
He said about 75km of strike of Magna Lynn had been completely overlooked by previous explorers.
Greater Duchess now has a project development team being assembled with Mick Breen appointed as project development manager.
Trekelano has three planned open-cut developments and has a $1.3 million environmental bond in place.