Bulk sample sorted as Orient testwork continues

Iltani Resources has successfully run a five-tonne bulk sample of Orient diamond drill core through a TOMRA ore sorting circuit as part of its metallurgical testwork process.

It comes as the company plans to release an updated mineral resource estimate by the end of the year for the Orient silver-indium project, located in the Herberton district.

Orient material post ore sorting (LHS conveyor is product, RHS conveyor is waste)

Iltani Resources (ASX: ILT) managing director Donald Garner said the Orient material was sorted using a Dual-Energy X-Ray Transmission (DE-XRT) process with TOMRA’s patented AI algorithm contAIn.

“The results were visually impressive, and 22 per cent of the feed material reported to product, 56 per cent to waste and 22 per cent to fines (less than 6.3mm size),” he said.

“The sorted sample has now been dispatched to Core Metallurgy in Brisbane for the next stage (flotation testwork) in the Orient metallurgical testwork process.”

The next steps will be:

  • Individual flotation tests: Conduct flotation tests on ore-sorting products and fines from each ore domain (high grade, medium grade and low grade) to understand their respective flotation characteristics, concentrate grades and metals recoveries.
  • Combined flotation tests: Recombine the sorted products and fines for each ore domain at their expected mass proportions and conduct flotation tests to assess the overall performance and identify any interactions between the materials.
  • Overall composite: Once suitable flotation conditions have been established, prepare a representative composite of the high grade, medium grade and low grade materials based on the anticipated plant feed proportions and conduct confirmation testwork.

Iltani holds about 370sq km of tenements in the Herberton Mineral Field, with most of the tenements located about 20km west of the historical mining town of Herberton.

A scoping study for the Orient project is set for completion in early 2027.