Bowen cracking along with Burton restart work

Bowen Coking Coal is fast-tracking work to bring its newly acquired Burton mine online while assessing the potential to boost production across its portfolio amid strong coal prices.

In a quarterly update, the company said refurbishment of the site’s CHPP was well underway and it had given mining contractor BUMA formal notice to start mobilising equipment for the mining of the Burton pits from January 1, 2023.

Bowen Coking Coal completed its acquisition of the mothballed Burton site in July after executing a deal with New Hope Corporation to gain a 90 per cent stake the Lenton joint venture for $20 million upfront and up to $77.5 million in royalties and milestone payments.

Work is well underway on the Burton CHPP refurbishment.

The company said refurbishment work was progressing well at the Burton accommodation facility, with 240 of the 350 rooms now fully operational.

“The company has enhanced the scope of the refurbishment program to include structural work on some units and an upgrade to the water, cooling and fire systems, in line with our long-term vision for the asset to support ongoing operations beyond the Burton mine only,” it reported.

“The fast-tracked refurbishment of the train load out (TLO) facility which provides Bowen with a direct path to market is ahead of schedule and, after exceptional performance from the Burton team, contractors and the Aurizon Network, the first trains are planned for early November.

“Work is well underway on the CHPP (coal handling and preparation plant) refurbishment in line with our strategy of bringing the first module on line as early as possible in the next year.”

The crushing circuit is expected to be recommissioned as a first stage and the initial module of the CHPP will be restarted in the first quarter of next calendar year.

It will be used to process material from the adjacent Broadmeadow East mine until open-pit mining operations are established at Burton.

“Additional drilling and studies are also underway to test potential resource extensions and revenue optimisation
options which could include further expansion of the CHPP capacity to maximise throughput of the complex,” Bowen Coking Coal stated.

The company is also producing coal from the Broadmeadow East pit, 25km north-east of Moranbah, and the Bluff mine, 20km east of Blackwater.

In its report to the market, Bowen Coking Coal said a strategic mine planning review was underway to assess potential for increased production volumes and mine life extensions across the portfolio amid strong coal prices.