Boots on the ground to advance vanadium mine plans
Site works have begun for a drilling program to underpin the definitive feasibility study for the Lindfield vanadium project, about 30km east of Julia Creek.
Project owner Critical Minerals Group said the program had been designed to meet a number of the geological, metallurgical, geotechnical, groundwater and mine planning requirements of the DFS.
It comes after the company released pre-feasibility study results in July confirming a pre-tax net present value of $821 million for a 3Mtpa mine development at Lindfield, to be complemented by a vanadium electrolyte manufacturing facility in New South Wales.
The Lindfield mineral resource estimate underpinning this stands at 713 million tonnes at 0.32 per cent vanadium pentoxide (comprising an indicated mineral resource of 491Mt and an inferred mineral resource of 222Mt).
Main image: Core from previous drilling at Lindfield
“Getting a rig on the ground ahead of the wet season keeps the DFS on schedule,” Critical Minerals Group (ASX: CMG) chief executive officer Pat Kelly said.
“This program does more than add holes to the resource. The core it produces goes straight into the metallurgical work that will settle recovery and reagent consumption, which the PFS identified as the variables with the greatest influence on project value.
“The groundwater and geotechnical data also start the approvals and engineering work that runs alongside the study. It is the first step in taking Lindfield from a completed PFS to a project that can be financed.”
Related: Funds boost to take vanadium project to next level
J&S Drilling is set to be mobilised to site next week for a drilling program of about 55 core holes for approximately 1320m (up to three to be completed as groundwater monitoring bores). Eight shallow geotechnical auger holes are also planned.
Geological supervision is being provided by Measured Group.
Selected sites will be twinned to provide about three tonnes of core samples for bench-scale variability test work and feed for the metallurgical pilot plant program.
It comes as the company marks a tenure win that means all mineralised material in the PFS mine plan is now held within its Lindfield permit (EPM 27872).
The Queensland Department of Natural Resources and Mines has approved the addition of land on the north-western portion of EPM 27872 that was previously excluded from CMG’s permit because of a historical overlap with MDL 522.
The PFS had identified the exclusion as a high-rated risk in the resources and reserves category, noting that if the mineralised material in the excluded area could not be included in the project it could reduce the mineralised material available to the mine plan by as much as about 20 per cent.
“Securing this land brings the whole of the Lindfield PFS mine plan within our permit,” Mr Kelly said.
“It is a strong outcome from 18 months of constructive engagement with the department, and it means we can drill the area in our DFS program and progress our project approvals with the full mine plan area in hand.”
The company said it would recommence its project approvals work, including a Coordinated Project application to the Queensland Coordinator-General, the environmental impact statement, the mining lease application and the referral under the Environment Protection and Biodiversity Conservation Act 1999.